PRELIMINARY PROJECT APPROVAL DEFINITION PHASE

PROJECT MILESTONES May 2004 to November 2011 TARGET END DATES STATUS
Treasury Board(TBS) Approval May 2004 Completed May 3, 2004
Completion of Requirements Specifications September 2004 Completed September 2004
Release of Draft Request for Proposal(RFP) May 2004 Completed May 25, 2004
Industry Feedback July 2004 Completed July 2004
Preparation and Release of Final(RFP) October 2004 Completed October 22, 2005
RFP Closure January 2005 CompletedJanuary 31, 2005
Bid Evaluation and Vendor Selection June 2005 Completed May 27, 2005
Contract Award for Implementation Fall 2005 TB approved contract award October 31, 2005. Contract signed with EDS Canada Inc. November 4, 2005
Project Start-up November 2005 Completed
Requirements Mapping and Gap Analysis May 2006 Completed June 2006
Architecture and Design September 2006 Completed September 2006

Effective Project Approval ( EPA ) TB Submission Including Detailed Implementation Plans

PROJECT MILESTONES May 2004 to November 2011 TARGET END DATES STATUS
June 2007 In Progress
EPA Start-up Activities November 2007 Completed
Design, Construction Implementation of GCPMP Solution November 2011 In Progress
  • Release 1.0 - Client Services Basic Case Management and Interactive Voice Response ( IVR )
December 2008 Implemented December 15, 2008
  • Release 1.1 - Telephony components
February 2009 Implemented February 2, 2009
  • Release 1.5 - Enhanced Case Management and Imaging
September - December 2009 In Progress - activities began in June 2008
  • Release 2.0 - Contributors
May 2010 In Progress - activities began in January 2008
  • Release 2.5 - Service Acquisition, Leave Without Pay (LWOP), Pension Benefits Division Act (PBDA)
July 2010
  • Release 3.0 - Annuitants and Accounting
October 2011
Final Maintenance Transition November 2011

Close Out Phase

PROJECT MILESTONES May 2004 to November 2011 TARGET END DATES STATUS
CLOSE OUT PHASE Post Implementation Review November 2011