Project Reporting
Green Optimal Performance |
Yellow Not currently in line with the baseline, but within approved parameters |
Red At risk of requiring new approvals. Not within approved parameters |
|
---|---|---|---|
Time Footnote 1, Footnote 2 OT - On Time |
The project milestones are currently in line with the approved schedule. The overall project completion date will also be respected. |
The project milestones are not currently in line with the approved schedule, but the overall project completion date will be respected. A comment must support this entry. |
The project milestones are not currently in line with the approved schedule, nor will the overall approved timeline be respected. An action plan must support this entry. |
Budget Footnote 1, Footnote 3 OB - On Budget |
The project current expenditures and forecasted expenditures are within the approved Expenditure and Project Authorities. | The project current expenditures are not in line with the plan, but the forecasted expenditures (including the risk allowance) do not exceed the expenditure authority or the Project Authority. A comment must support this entry. |
The project current expenditures forecast exceed the expenditure authority or the Project Authority. An action plan must support this entry. |
Scope Footnote 1, Footnote 4 OS - On Scope |
The project requirements (scope) are known and requirements changes have no impact on the project. | The project requirements are not clear. The requirements changes may impact the project negatively. A comment must support this entry. |
The project requirements are not known. The requirements changes will impact negatively the project. An action plan must support this entry. |
Green Optimal Performance |
Yellow Not currently in line with the baseline, but within approved parameters |
Red At risk of requiring new approvals. Not within approved parameters |
|
---|---|---|---|
Time Schedule status should be measured against the approved baseline for the project, and the adherence to the schedule of deliverables. |
|
|
|
Budget Budget status should be measured against the approved baseline for the project. |
|
|
|
Scope Scope status should be measured against the approved baseline for the project. |
|
|
|