Close out document for asset, other government department and tenant service projects
The purpose of this document is to mark the completion of the project by confirming that essential deliverables, documents and other project closure activities have been completed and lessons learned identified.
This table lists the required National Project Management System (NPMS) deliverables at the delivery close out of asset crown-owned, other government department (OGD) and tenant service projects, whether they are required or not for NPMS full, lite or ultra lite, when and by who they were approved, and where the documents are located. (This table is only for example and contains no data. A dot means the document is required.)
Responsibility | NPMS deliverable documentsFootnote 1 | Project execution stream requirements | Approved by / date | Electronic project filing structure (EPFS) document location (Note: delete file reference and indicate file location if different from EPFS location) |
|||||
---|---|---|---|---|---|---|---|---|---|
Asset crown - ownedFootnote * | Other government services (OGD) Footnote ** | Tenant serviceFootnote ** | |||||||
Full (F)Footnote 2 | Ultra lite (UL)Footnote 3 | F | UL | F | UL | ||||
Project leader (PL) | Approved simplified statement of requirements (S-SOR) | • | • | A_NPMS\01_Definition\statement of requirements approval | |||||
Project manager (PM) | Signed project charter (PC) | • | • | • | • | A_NPMS\06_Planning\OGD project charter Approval | |||
PM | Specific service agreement (SSA) | • | • | • | • | F_CLIENTS\01_Agreement\SSA | |||
PM | Approved project management plan (PMP) | • | • | • | A_NPMS\06_Planning\project management plan approval | ||||
PM | Approved simplified project management plan (S-PMP) | • | • | • | A_NPMS\06_Planning\project management plan approval | ||||
PL | Approved long form investment analysis report (LF-IAR) (and Treasury Board (TB) submission if required) |
• | A_NPMS\07_Design\IAR Signed (EA) A_NPMS\07_Design\TB Submission (EA) |
||||||
PL | Approved short form investment analysis report (SF-IAR) (when an amended SF-IAR project approval (PA) / expenditure authority (EA) submission is not required to be sought, an approval document (AD) is required to be provided) |
• | A_NPMS\07_Design\IAR Signed (EA) | ||||||
PM | Approval document (AD) (documented evidence of project leader acceptance of design development drawings and substantive construction cost estimate) |
• | • | • | • | A_NPMS\07_Design | |||
PM | Product turn-over (PTO) (signed certificate of substantial performance (Interim)) |
• | • | • | • | • | • | C_CONSTRUCTION\Contract X\16_Certificate Substantial Performance\Signed Cert Subst Perf (S34) | |
PM | Lessons-learned log | • | • | • | • | • | • | A_NPMS\05_Identification Close Out\Lessons Learned Documents | |
PM | Lessons-learned report (required for projects with PCRA level 3 or higher, or for OGD projects over $10M) | • | • | • | A_NPMS\05_Identification Close Out\Lessons Learned Documents | ||||
PM | Approved close out document (COD) | • | • | • | • | • | • | A_NPMS\08_Delivery Close Out\close out document approval (CODA) |
This table lists the required supporting documents at the delivery close out of asset crown-owned, other government department (OGD) and tenant service projects, whether they are required or not for NPMS full or ultra lite, whether they are completed or not, and where the documents are located. (This table is only for example and contains no data. A dot means the document is required.)
Responsibility | NPMS support documents | Project execution stream requirements | Completed (Yes / No / Not applicable) |
Electronic project filing structure (EPFS) document location (Note: delete file reference and indicate file location if different from EPFS location) |
|||||
---|---|---|---|---|---|---|---|---|---|
Asset crown - owned Footnote * | OGD Footnote ** | Tenant service Footnote ** | |||||||
F | UL | F | UL | F | UL | ||||
PL | Signed identification close out document (ICOD) | • | • | A_ NPMS\05_identification close out\Identification close out document (ICOD) | |||||
PM | Environmental compliance management program (ECMP) checklist | • | • | • | • | • | • | I_SPECIALIZED AREAS\Environmental Requirements\ECMP Checklist | |
PM | Preliminary identification of env. services required (PIESR) | • | • | • | • | • | • | I_SPECIALIZED AREAS\Environmental Requirements\PIESR | |
PM | Commissioning assessment form | • | • | • | • | C_CONSTRUCTION\Contract X\14_Deliverables\Commissioning Docs | |||
PM | Risk management plan (project risk assessment, risk register, monitoring record) | • | • | • | • | • | • | A_ NPMS\09_ NPMS Supporting Documents\Risk Management Plan | |
PM | Project master schedule | • | • | • | • | • | • | H_PROJECT MONITORING\01_Project Time Scope Budget\Schedule | |
PM | Project review advisory committee (PRAC) Minutes | • | • | • | A_ NPMS\09_ NPMS Supporting Documents\PRAC | ||||
PL | Revised project complexity and risk assessment (PCRA) (if required to be revised) | • | A_ NPMS\09_ NPMS Supporting Documents \PCRA | ||||||
PM | Substantive cost estimate (required for EA beyond the design phase, and to obtain amended PA if required; SSA values required for OGD and Tenant Service projects) |
• | • | • | • | • | • | H_PROJECT MONITORING\01_Project Time Scope Budget\Budget | |
PM | Construction change order log | • | • | • | • | • | • | C_CONSTRUCTION\Contract X\06_Change Orders\Change Order Log | |
PM | As-built documentation and O&M Manuals | • | • | • | • | • | • | C_CONSTRUCTION\Contract X\14_Deliverables\As-built Drawing C_CONSTRUCTION\Contract X\14_Deliverables\O and M Manuals |
|
PM | OGD client acceptance letter | • | • | • | • | A_ NPMS\08_Delivery Close Out | |||
PM | Completed SIGMA performance indicators (for schedule, cost, scope) |
• | • | • | Not Applicable | ||||
PM | Consultant performance evaluation report form (CPERF) | • | • | • | • | • | • | B_SERVICES\Service Contract X\07_Contract Close out\CPERF | |
PM | Contractor performance evaluation report form (CPERF) | • | • | • | • | • | • | C_CONSTRUCTION\Contract X\19_Contract Close out\CPERF | |
PM | Commissioning report (if required) | • | • | • | • | • | • | C_CONSTRUCTION\Contract X \14_Deliverables\Commissioning Docs | |
PM | Functional/technical program (if required) | • | • | • | • | F_CLIENTS\01_Agreement\functional program | |||
PM | Signed certificate of completion (Final) (Note: completion of this document and the required NPMS project execution stream deliverable and support documents identified above, constitute NPMS project delivery close out.) |
• | • | • | • | • | • | C_CONSTRUCTION\Contract X\17_Certificate Completion |
Prepared by:
Signature
Please print:
Name – Title (role of project manager) – Date
Agreed by:
Signature
Please print:
Name – Title
(role of project leader) – Date:
Approved by:
Signature
Please print:
Name – Title (For NPMS Full: role of project director / Regional manager project management; For NPMS ultra lite: Senior project manager) – Date
This table lists the post project delivery close out activities of asset crown-owned, other government department (OGD) and tenant service projects, whether they are completed or not, and where the documents are located. (This table is only for example and contains no data. A dot means the document is required.)
Responsibility | Post project delivery close out activities | Project execution stream requirements | Completed (Yes / No / Not applicable ) |
Electronic project filing structure (EPFS) document location (Note: delete file reference and indicate file location if different from EPFS location) |
|||||
---|---|---|---|---|---|---|---|---|---|
Asset crown - owned Footnote * | OGD Footnote ** | Tenant service Footnote ** | |||||||
F | UL | F | UL | F | UL | ||||
PM | Completed warranty files (if applicable) | • | • | • | • | • | • | C_CONSTRUCTION\Contract X\14_Deliverables\Warranties | |
PM | Completed contract files | • | • | • | • | • | • | B_SERVICES\Service Contract X \01_Consultant Contract\Contract Docs\Signed Contract (S32) C_CONSTRUCTION\Contract X \01_Contract\Contract Docs\Signed Contract (S32) E_GOODS\Goods Contract X \01_Supplier Agreement\Contract Docs\Signed Contract (S32) |
|
PM | Project closed out in SIGMA | • | • | • | • | • | • | Not applicable |
Prepared by:
Signature
Please print:
Name – Title (role of project leader) – Date
- Date modified: