Design-Bid-Build Projects roadmap

Delivery Stage

Introduction

This Design-bid-build (DBB) Projects Roadmap is based on main activities and tasks required to manage the delivery of construction projects. DBB delivery methodology involves planning, architecture and engineering design by consultant or Public Services and Procurement Canada (PSPC), followed by engaging a contractor to construct the project based upon design. Contractual coordination for both design and construction is the responsibility of PSPC.

This roadmap is not intended to cover in detail activities related to the DBB process but rather provides a high level overview for the project delivery stage activities from the time that a preliminary project approval has been obtained and the Identification Stage Close Out Phase activities have been completed. For steps to be taken during these front-end stages, see either:

This roadmap is intended to be used as a guide for those having the role of Accommodation Manager, Project Leader or Project Manager. Relevant links are indicated for specific business line information, processes and templates to be used.

National Project Management System (NPMS) procedures apply to all space-based projects over 3000  rentable (regions) or 5,000  rentable (National Capital Area / Parliamentary Precinct), and for asset-based projects, over $1M total value (including Goods and Services Tax (GST) or Harmonized Sales Tax (HST) and excluding any client costs). For projects under these limits, NPMS principles remain applicable, however the level of effort and extent of documentation will vary depending upon a number of factors including the project size and complexity as well as the sensitivity of the project. For these smaller projects, see the principles of the National Project Management System (page available on Government of Canada network only).

Project delivery stage

Planning Phase

Objective

The purpose of the Planning Phase is to confirm the quality and completeness of the existing project information in an effort to develop and organize the project delivery strategy.

Description of the Work

During this phase, all previous parameters of the project are validated and an agreement for delivery is reached or re-confirmed between the Project Leader and Project Manager.

Inputs

Activities / Tasks

  1. Start-up Stage
    1. Inform the Technical Experts (Architecture & Engineering), Regional Construction Safety Coordinator, Environmental Specialists and other stakeholders about the project
    2. Refine Project Team
    3. Identify security, environmental and health & safety requirements
    4. Conduct assessment of Commissioning requirements
    5. Review existing Lessons Learned from similar projects
    6. Review Preliminary Workplace 2.0 Accreditation Evaluation Grid
    7. Update functional program, as required
    8. Update cost estimates and schedules
    9. Create Project management plan
    10. Create / Update Project charter
    11. Create specific service agreement (SSA) (if required)
    12. Update Project File Structure (financial codes, confirm funds, etc.). Designation of Project as Capital (to be capitalized) or Repair (to be expensed) as determined in definition phase.
  2. Define Project Delivery
    1. Confirm Functional and Technical Program
    2. Define consultant scope of work
    3. Consider Components of the project brief (Terms of Reference)
    4. Create/Update Risk Management Plan
    5. Submit project management plan for review by Project Review Advisory Committee (PRAC) as necessary (i.e. peer, regional or national review)
    6. Complete Planning Phase Checklist

Outputs

Deliverable

Project management plan (PMP)

Control point

Project management plan approval (PMPA)

Design Phase

Objective

To award all relevant consultant contracts to the most qualified bidders, as well as refine the proposed design concept into a detailed, and final design version of required specifications. This final design will typically require amendments to preliminary projections of time, cost, quality, and perhaps scope. All completed documents are compiled to form the basis for the effective project approval (EPA) submission. This approval is required in order to proceed with construction implementation.

Description of the Work

Procurement of required resources makes way for detailed design and establishment of refined specifications. Reviews, approvals, and risk assessments are critical during this stage. effective project approval (EPA) is sought upon completion and assembly of all detailed plans for project delivery.

Inputs

Activities / Tasks

  1. Procure Consultant Services
    1. Write project brief (Terms of Reference)
    2. Update Risk Management Plan
    3. Provide input to ensure the pre-approved amount for anticipated amendments (PAAA) is established for Consultant Contract
    4. Prepare Request for proposal (Procurement Methodologies Footnote 1)
    5. Conduct Consultant Evaluation (Conduct Procurement Footnote 1; Consultant Evaluation Board Membership)
    6. Award Consultant Contract
  2. Develop Design
    1. Complete Analysis of Project Requirements
    2. Develop Concept Design and Design Development Documents for approval by client (Review and Acceptance of Consultant Design and Construction Documents)
    3. Prepare furniture layouts for approval by client (if applicable)
    4. Prepare Furniture and Equipment and Systems Procurement Documents (if applicable)
    5. Review for non-compliance with Base Building and Archived—The Government of Canada Workplace 2.0 Fit-up Standards and obtain approval as required
    6. Update the Workplace 2.0 Accreditation Evaluation Grid
    7. Incorporate any reviews, reports, and/or recommendations initiated through the PIESR
  3. Prepare for Approval
    1. Finalize cost estimates and schedules
    2. Reconfirm or update the Project complexity and risk assessment
    3. Update investment analysis report (IAR)
    4. Update key parameters of the PMP
    5. Revise ECMP Checklist if project scope has changed significantly
    6. Incorporate recommendations from Commissioning Assessment
    7. Complete Design Phase Checklist

Outputs

Deliverables

Control point

Effective project approval

Implementation Phase

Objective

The purpose of the Implementation Phase is to produce an end product of acceptable quality that meets client requirements.

Description of the Work

The Implementation Phase is where all the plans and related strategies are put into motion. All construction-related (or physical work) activities are carried out.

Inputs

Activities / Tasks

  1. Finalize Construction Documents and Procure Construction Services
    1. Complete Construction Documents (Review and Acceptance of Consultant Design and Construction Documents). Develop design drawings/specifications to 33-66-99% (33-99% for road construction projects)
    2. Conduct review at 33-66-99% (33-99% for road construction projects)
    3. Submit notification/application for environmental permits (if required)
    4. Sign-off on final drawings/specifications
    5. Review designation of project to confirm it should remain as Capital (to be capitalized) or Repair (to be expensed) and make necessary changes in SIGMA
    6. Compile Construction Tender Documents (Procedures for Construction Services Footnote 1)
    7. Review environmental submission (if required)
    8. Update Risk Management Plan
    9. Provide input to ensure PAAA is established for Construction Contract
    10. Conduct Tender Call and Evaluation (Conduct Procurement Footnote 1)
    11. Obtain all necessary permits that are not the responsibility of the contractor
    12. Award Construction Contract
  2. Construct
    1. Conduct start-up and subsequent construction meetings
    2. Administer construction Contract (Administer the Contract Footnote 1)
    3. Ensure adherence to construction site safety
    4. Ensure adherence to recommendations and/or mitigation measures related to environmental reports and reviews
    5. Monitor budget and construction progress and keep Project Leader informed
    6. Perform Commissioning during Construction (Commissioning Manual)
  3. Accept Work
    1. Test Functional Performance (Commissioning Manual)
    2. Conduct material quality testing and review test results (if required for road construction projects)
    3. Compile Commissioning Documents
    4. Assemble As-Built Documents
    5. Ensure Training is provided and Operating and Maintenance (O&M) Manuals delivered
    6. Review deficiency report(s) and notify the contractor to correct deficiencies if necessary
    7. Issue Certificate of Substantial Performance (Interim)
    8. Advise Finance of Substantial Completion
    9. Return contracts securities (including hold-backs)
    10. Transfer Site to Real Property Manager
    11. Client Move-in
    12. Update key parameters of the PMP
    13. Document Lessons Learned
    14. Complete Implementation Phase Checklist

Outputs

Deliverable

Product Turn-Over (PTO) (Certificate of Substantial Performance)

Control point

Turn-Over Approval (TOA)

Delivery Stage Close Out Phase

Objective

In an effort to improve overall project performance and client satisfaction, both product and process performance will be documented and assessed against pre-determined performance criteria. The process of Continual Improvement is imperative to the overall enhancement of project delivery within PSPC. The basis for the continual improvement process is its encapsulation of both positive and negative elements of the project.

Description of the Work

The Delivery Close Out Phase is the final and most integral stage of the project. It not only gives the team the opportunity to tie-up all loose ends, but it allows for a thorough assessment of all aspects of the project. This assessment underscores any performance targets that were reached, surpassed or not met. In addition, the Continual Improvement Process provides a valuable method for highlighting successes as well as deficiencies reported throughout the life of the project. These records form the basis for systematic improvements to the way similar projects will be delivered in the future. The Close Out Phase includes two major activities: 1. Close-outs of contracts (the activity whereby all aspects of the performance and conformance of the end product with respect to specific equipment, installation or services provided are evaluated), 2. Close Project (the activity of gathering and assessing project performance data).

Inputs

Activities / Tasks

  1. Close-outs of Contracts
    1. Perform Post-Occupancy Inspection
    2. Issue Certificate of Completion (Final)
    3. Perform Warranty Activities
    4. Initiate Consultant Performance Evaluation Report (CPERF)
    5. Initiate Contractor Performance Evaluation Report (CPERF)
    6. Finalize Contract(s) (Contract Close-out Footnote 1)
  2. Close Project
    1. Execute Final Space Measurement
    2. Ensure Occupancy Instrument is in place
    3. Gather End-User Feedback, and finalize lessons learned
    4. Submit the Completed Workplace 2.0 Accreditation Evaluation Grid to wp2.mt2@tpsgc-pwgsc.gc.ca
    5. Send as-builts to the regional Geomatics group (if applicable) to allow updates of current drawings
    6. Complete Administrative Close Out Activities for contracts
    7. Complete close out document
    8. Complete final recording of documents

Outputs

Deliverable

Close out document (COD)

Control point

Close out document approval (CODA)

Date modified: