National Training for Commissioning 2006
Presented by Paul Sra and Mike Cavan
Scope of Presentation
- Commissioning overview
- Commissioning requirements for Leadership in Energy and Environmental Design (LEED) Standard
- Roles and responsibilities of key persons for projects in regard to commissioning
- Commissioning process and its deliverables
- Case studies
What is Commissioning
- American Society of Heating, Refrigerating and Air-conditioning Engineers (ASHRAE) defines the commissioning process as "a quality oriented process for achieving, verifying and documenting that the performance of facilities, systems and assemblies meet the defined objectives and criteria"
- Commissioning is a quality assurance process where verification against design criteria is carried out, and ensures that adequate documentation and O&M training has been provided
- A planned program of activities that advances the built works from the earliest phases of the project identification stage to a condition of full operation, meeting all objectives of commissioning as defined by the client's functional program and the design intent. Commissioning is documenting for future operations
Commissioning Requirements for Leadership in Energy and Environmental Design Standards
For any LEED project, there are 6 fundamental Commissioning items that must be followed to attain LEED Certification:
- Engage a Commissioning Manager/Commissioning Authority
- Review Design Intent and other Design documentation
- Include Commissioning requirements in Construction Specifications
- Develop and utilize a Commissioning Plan
- Verify installation, functional performance, training and Commissioning documentation
- Provide a final Commissioning report at the end of the project
Securing the Additional Commissioning Credit in the Leadership in Energy and Environmental Design System
In addition to fundamental building Commissioning, an additional commissioning related point could be achieved:
- Commissioning Authority independent of the design team shall conduct a peer review of the design development, construction documents and contractor's submittals such as shop drawings
- Provide a single manual containing all information required for re-commissioning the bldg. system
- Conduct a near end of warranty and plan to address occupant concerns
Why do we Commission
We Commission in order to provide a smooth transition from construction of the built works to an operational state.
Level / Extent of Commissioning
In order to manage the cost and result of the commissioning process, owners must consider the following three basic questions:
- What systems should be commissioned
- What tasks should be completed in order to commission each system
- Who should be responsible for each task
- Other factors: Type of project, new construction, fit-up, general purpose office, laboratory, Heritage Facility
Complexity of project
Is it a Floor fit-up or Level 3 Lab: Heating, Ventilating, and Air-conditioning (HVAC) Containment / Fumehoods / Biological Safety Cabinets?
- Profile of project
- LEED Certification
Commissioning of Total Building Systems
Facility
- Building Envelope
- Integrated Mechanical and Electrical
- Architectural, Roof system, curtain wall system
- Life Safety Systems
- Heating and Cooling Plant
- Emergency Power Generation
- Indoor Environment
- Integrated Security
- Electrical Distribution
- Building Automation system (BAS)
- Vertical Transportation
Benefits of Commissioning
- Comprehensive understanding of Client's needs (such as functional and operational requirements)
- Reduce tenant complaints and reduce O&M costs (by providing appropriate systems and equipment considering maintainability)
- Indoor air quality parameters verified
- Protection of health and safety of occupants (e.g. verification of Fire protection, life safety systems, security and operation of facility)
- Meet established energy budgets
- Facilitates quality of construction and installation
- Comprehensive training and documentation
- Reduce risk of system failure/shutdown
When does Commissioning start
Commissioning starts at the project identification stage and continues throughout all phases of the project. Commissioning supports total quality assurance in the design and development of facilities to meet client's needs
Commissioning Activities in the National Project Management System: Who is Involved
Commissioning involves an integrated team comprising of the:
- Owner/Client
- Project Manager
- Commissioning Manager / Authority
- Designer (Consultant)
- Contractor
- Property Manager
Owner / Client Responsibilities
- Provides program requirements (technical and functional)
- Defines performance objectives and standards (technical data sheets)
- Sets Budgets and Schedules (milestones)
- Participates in selective Performance Tests
- Attends Training
- Participates to Interim acceptance process
Project Manager Responsibilities
Overall responsibility for delivery of the project (of which Commissioning is part)
- Manages:
- Contracts (consultants, contractors, client)
- Relationship (Professional and Technical Services, Owner, Consultants, Commissioning Manager, Contractors, Property Manager
- All funding
Commissioning Manager / Authority Responsibilities
- Coordinates Commissioning activities with the project team
- Carries out Quality Assurance on behalf of the Owner / Investor, Project Manager and Property Manager
- Reviews "Commissioning Plan" to ensure that plan is tailored to facility requirements
- Manages Commissioning process
Reviews:
- and accepts Designer developed Commissioning specifications which include check sheets and functional performance tests.
- Design Intent and Concept drawing
- Design progress drawings (33%, 66%, 99%, 100% and tender drawings)
- O&M Manuals
- Witnessing of equipment, system and Integrated and system performance tests
Design Consultant Responsibilities
- Liable and accountable
- Develops the "Commissioning Plan"
- Produces the Commissioning manual and Design Intent
- Develops the "Commissioning Specifications"
- Develops the "Training Plan"
- Develops the Commissioning forms (Product Information / Performance Verification (PI/PV) and checklists)
- Develops and certifies the functional performance tests
- Administers and reports on the commissioning process with the Contractor
- Provides approvals on verifications and testing
- Witnesses testing (as required)
- Assists in documentation turnover
General Contractor Responsibilities
- Accountable contractually
- Executes the commissioning deliverables as defined in the contract documents
- Develops the Commissioning schedule
- Refines the Commissioning Plan
- Executes and documents the functional performance (tests)
- Prepares and submits the O&M manual, training, as-builts, warranties
Property Manager Responsibilities
- Receives the facility once project is complete
- Receives all documents required for operation
- Manages the facility
- Implements the Management Plan (Building Management Plan, Maintenance Management System, Service contracts)
- Operates the facility through out its useful life
The Commissioning Process
The Commissioning Process is based on the phases of the National Project Management System (NPMS)
- Project inception stage
- Definition phase
- Project identification stage
- Initiation phase
- Feasibility phase
- Analysis phase
- Identification Close-out phase
- Project delivery stage
- Planning phase
- Design phase
- Implementation phase
- Delivery Close-out phase
- Project inception / project identification stage
- Owner identifies the project's operation and functional requirements as well as sets budgets and milestones
- Establishes Commissioning needs
- Project delivery stage: Planning phase
- A list of commissioning deliverables is identified and is included in the consultant brief (request for proposals, scope of work)
- This includes definition of building O&M and user requirements
- A Commissioning Manager (for the project) is appointed
- Project delivery stage: Design phase
- Develop design intent
- Preliminary O&M and energy budget
- Prepare "Preliminary Commissioning Plan" to meet facility requirements and users needs within the facility
- Project delivery stage: Implementation phase
- Develop Building Management Manual
- Review design to ensure facility needs have been addressed
- Finalize commissioning plan
- Develop specification and performance verification forms to permit effective commissioning of the facility
- Develop a "Training Plan" to meet the requirements of the facility operators
- Provide input to requirements for the construction phase and establishes an O&M budget
- Review the Building System Shop Drawings for O&M
- Develop the Commissioning Schedule
- Finalize the "Commissioning Plan"
- Completion of Product Information / Performance Verification (PI/PV) forms
- Site Coordination Meetings
- Complete the installation checklist
- O&M Manuals
- As-Built drawings
- Warranties
- Equipment, systems and integrated systems commissioning tests are performed and witnessed
- Operational and Maintenance Manual(s) are completed
- Finalize Building Management Manual
- Ensure Commissioning deliverables are provided
- Interim acceptance is recommended to the Project Manager
- Ensure training of O&M staff is completed
- Project delivery stage: Close Out (Phase 1)
- Complete all deferred commissioning tests and activities
- assist in the fine tuning of systems
- complete all outstanding design and construction (contractual) deficiencies relating to O&M issues
- Recommend final acceptance to the project manager
- Project delivery stage: Close Out (Phase 2)
- Project Team evaluation of lessons learned
- Assist the project manager in preparation of the final evaluation report
Summary—Commissioning Deliverables
- Commissioning Plan
- Design reviews for O&M impacts
- Design Intent / System Operating Manual
- Commissioning Specifications
- Commissioning Performance testing (PI/PV and checklists)
- Commissioning schedule
- Training
- Operation and Maintenance manuals (O&M)
- As-Built drawings
- Warranty (Documentation)
Commissioning: Return on Investment
- Can reduce operational and maintenance costs (through effective recommendation in the selection of equipment)
- Results in a product delivery with fewer deficiencies
- Reduces tenant complaints
- Reduces operational surprises
- Operational savings offset commissioning costs in one to two years
- Extended lifecycle on equipment
- Reduces changes during and after construction
Retro Commissioning
- Energy Management and Control Systems (EMCS) and Lighting Systems
- Objectives:
- Identify energy deficiencies
- Optimization of systems
- Identify HVAC Indoor Air Quality issues
- Constructed early 70's
- Existing mechanical systems
- EMCS approx. 10 years old
- Lighting system approx. 6 years old
- Involved Operations Staff
- Involved the EMCS / Lighting Service providers
- Involved the field device maintainer
- Will involve an Energy Engineer
Verifications performed on EMCS:
- Field sensors and devices
- Sequence of operations under normal / Emergency procedures
- Trending of systems
Key EMCS Issues Identified:
- Damper performance / calibrations
- Variable Speed Drive's at 100% most of the time
- Induction units: 27% failure rate
- Pneumatic devices: transducer compatibility: 34% failure rate
- Operator Training
Major Building Issues:
- Stack effect
- Age of existing equipment
- Change in occupancy (space optimization)
- Minor fit-ups in building over the years
Lighting System: Areas of Interest
- Review current system operation and documentation
- Identify Maintenance Issues
- Identify energy saving potentials
- Commissioning of lighting system controls and devices
Key Lighting system issues
- Clock was not recognizing weekends and holidays
- DOS based Operator interface
- Failed relays
- Additional "Feature" lights not on system
- Daylight harvesting
- Change-out of tubes
- Operator training
- Date modified: