Project Schedule
The table describes the task names, duration, work days, and start and finish dates for the project schedule.
Task Name | Duration | Work | Start | Finish |
---|---|---|---|---|
Project Schedule | 30.07 days | 0 days | 4/1/2010 0:00 | 5/13/2010 9:30 |
Project Milestones | 30.07 days | 0 days | 4/1/2010 0:00 | 5/13/2010 9:30 |
Project Start | 0 days | 0 days | 4/1/2010 0:00 | 4/1/2010 0:00 |
Project End | 0 days | 0 days | 5/13/2010 9:30 | 5/13/2010 9:30 |
Management & Control | 2 days | 0 days | 4/1/2010 8:00 | 4/6/2010 16:00 |
Project Management | 2 days | 0 days | 4/1/2010 8:00 | 4/6/2010 16:00 |
Scope Management | 1 day | 0 days | 4/1/2010 8:00 | 4/1/2010 16:30 |
Scope Management Plan | 1 day | 0 days | 4/1/2010 8:00 | 4/1/2010 16:30 |
Change review meetings | 1 day | 0 days | 4/1/2010 8:00 | 4/1/2010 16:30 |
Time Management | 1 day | 0 days | 4/1/2010 8:00 | 4/1/2010 16:30 |
Project Schedule | 1 day | 0 days | 4/1/2010 8:00 | 4/1/2010 16:30 |
Schedule review meetings | 1 day | 0 days | 4/1/2010 8:00 | 4/1/2010 16:30 |
Cost Management | 1 day | 0 days | 4/1/2010 8:00 | 4/1/2010 16:30 |
Project Budget | 1 day | 0 days | 4/1/2010 8:00 | 4/1/2010 16:30 |
Budget review meetings | 1 day | 0 days | 4/1/2010 8:00 | 4/1/2010 16:30 |
Quality Management Plan | 1 day | 0 days | 4/1/2010 8:00 | 4/1/2010 16:30 |
Human Resources (HR) Plan | 1 day | 0 days | 4/1/2010 8:00 | 4/1/2010 16:30 |
Communications Management | 2 days | 0 days | 4/1/2010 8:00 | 4/6/2010 16:00 |
Communications Plan | 1 day | 0 days | 4/1/2010 8:00 | 4/1/2010 16:30 |
Stakeholder assessment | 1 day | 0 days | 4/1/2010 16:30 | 4/6/2010 16:00 |
Initiate Information Technology Services Branch (ITSB) Dashboard Reporting | 1 day | 0 days | 4/1/2010 16:30 | 4/6/2010 16:00 |
Risk Management | 1 day | 0 days | 4/1/2010 8:00 | 4/1/2010 16:30 |
Risk Management Plan | 1 day | 0 days | 4/1/2010 8:00 | 4/1/2010 16:30 |
Risk review meetings | 1 day | 0 days | 4/1/2010 8:00 | 4/1/2010 16:30 |
Procurement Plan | 1 day | 0 days | 4/1/2010 8:00 | 4/1/2010 16:30 |
Information Management Plan | 1 day | 0 days | 4/1/2010 8:00 | 4/1/2010 16:30 |
Governance | day | 0 days | 4/1/2010 16:30 | 4/6/2010 16:00 |
Establish Core Team, Project Steering Cttee, meeting schedule, Terms of Reference (TOR) | 1 day | 0 days | 4/1/2010 16:30 | 4/6/2010 16:00 |
National Project Management System (NPMS) Stages and Phases | 29 days | 0 days | 4/6/2010 8:00 | 5/13/2010 9:30 |
Inception Stage | 2 days | 0 days | 4/6/2010 8:00 | 4/7/2010 16:00 |
Definition | 2 days | 0 days | 4/6/2010 8:00 | 4/7/2010 16:00 |
Statement of requirements | 1 day | 0 days | 4/6/2010 8:00 | 4/6/2010 16:30 |
Screening Tool (L) | 1 day | 0 days | 4/6/2010 8:00 | 4/6/2010 16:30 |
Project complexity and risk assessments (PCRA) (F) | 1 day | 0 days | 4/6/2010 8:00 | 4/6/2010 16:30 |
Statement of requirements approval | 1 day | 0 days | 4/6/2010 16:30 | 4/7/2010 16:00 |
Identification Stage | 13 days | 0 days | 4/7/2010 16:00 | 4/26/2010 8:30 |
Initiation | 4 days | 0 days | 4/7/2010 16:00 | 4/13/2010 14:00 |
Preliminary project plan | 1 day | 0 days | 4/7/2010 16:00 | 4/8/2010 15:30 |
Business Deliverables | 1 day | 0 days | 4/7/2010 16:00 | 4/8/2010 15:30 |
Business Change | 1 day | 0 days | 4/7/2010 16:00 | 4/8/2010 15:30 |
Business Requirements | 1 day | 0 days | 4/7/2010 16:00 | 4/8/2010 15:30 |
Target Business Vision | 1 day | 0 days | 4/7/2010 16:00 | 4/8/2010 15:30 |
Concept Independent Review | 1 day | 0 days | 4/8/2010 15:30 | 4/9/2010 15:00 |
Information Management / Information Technology (IM/IT) Architechture Review Board (ARB) | 1 day | 0 days | 4/9/2010 15:00 | 4/12/2010 14:30 |
Preliminary project plan approval | 1 day | 0 days | 4/12/2010 14:30 | 4/13/2010 14:00 |
Feasibility | 4 days | 0 days | 4/13/2010 14:00 | 4/19/2010 11:00 |
Feasibility report (F) | 1 day | 0 days | 4/13/2010 14:00 | 4/14/2010 13:30 |
Business Deliverables | 1 day | 0 days | 4/13/2010 14:00 | 4/14/2010 13:30 |
Procurement | 1 day | 0 days | 4/13/2010 14:00 | 4/14/2010 13:30 |
Corporate and Organizational Requirements | 1 day | 0 days | 4/13/2010 14:00 | 4/14/2010 13:30 |
Architecture | 1 day | 0 days | 4/13/2010 14:00 | 4/14/2010 13:30 |
Architecture Solution (Conceptual Version) | 1 day | 0 days | 4/13/2010 14:00 | 4/14/2010 13:30 |
Technical Solution | 1 day | 0 days | 4/13/2010 14:00 | 4/14/2010 13:30 |
Concept of Operations | 1 day | 0 days | 4/13/2010 14:00 | 4/14/2010 13:30 |
Approach Independent Review | 1 day | 0 days | 4/14/2010 13:30 | 4/15/2010 12:00 |
Business Operations Committee (BOC) | 1 day | 0 days | 4/15/2010 13:00 | 4/16/2010 11:30 |
Feasibility report approval (FRA) | 1 day | 0 days | 4/16/2010 11:30 | 4/19/2010 11:00 |
Analysis | 4 days | 0 days | 4/19/2010 11:00 | 4/23/2010 9:00 |
Business Case | 1 day | 0 days | 4/19/2010 11:00 | 4/20/2010 10:30 |
Client approval | 1 day | 0 days | 4/19/2010 11:00 | 4/20/2010 10:30 |
Project charter | 1 day | 0 days | 4/19/2010 11:00 | 4/20/2010 10:30 |
Client approval | 1 day | 0 days | 4/19/2010 11:00 | 4/20/2010 10:30 |
PCRA Update (F) | 1 day | 0 days | 4/19/2010 11:00 | 4/20/2010 10:30 |
Client approval | 1 day | 0 days | 4/19/2010 11:00 | 4/20/2010 10:30 |
Screening Tool Update (L) | 1 day | 0 days | 4/19/2010 11:00 | 4/20/2010 10:30 |
Client approval | 1 day | 0 days | 4/19/2010 11:00 | 4/20/2010 10:30 |
Business Deliverables | 1 day | 0 days | 4/19/2010 11:00 | 4/20/2010 10:30 |
Business Change | 1 day | 0 days | 4/19/2010 11:00 | 4/20/2010 10:30 |
Business Transformation Strategy | 1 day | 0 days | 4/19/2010 11:00 | 4/20/2010 10:30 |
Engagement Strategy | 1 day | 0 days | 4/19/2010 11:00 | 4/20/2010 10:30 |
Release Strategy | 1 day | 0 days | 4/19/2010 11:00 | 4/20/2010 10:30 |
Requirements Traceability Matrix | 1 day | 0 days | 4/19/2010 11:00 | 4/20/2010 10:30 |
Procurement | 1 day | 0 days | 4/19/2010 11:00 | 4/20/2010 10:30 |
Financial Proposal | 1 day | 0 days | 4/19/2010 11:00 | 4/20/2010 10:30 |
Requirements & Pricing Tables | 1 day | 0 days | 4/19/2010 11:00 | 4/20/2010 10:30 |
Statement of requirements | 1 day | 0 days | 4/19/2010 11:00 | 4/20/2010 10:30 |
Request for Information Documents | 1 day | 0 days | 4/19/2010 11:00 | 4/20/2010 10:30 |
Service Requirements Evaluation Criteria | 1 day | 0 days | 4/19/2010 11:00 | 4/20/2010 10:30 |
Privacy | 1 day | 0 days | 4/19/2010 11:00 | 4/20/2010 10:30 |
Preliminary Privacy Impact Assessment | 1 day | 0 days | 4/19/2010 11:00 | 4/20/2010 10:30 |
Privacy Impact Assessment | 1 day | 0 days | 4/19/2010 11:00 | 4/20/2010 10:30 |
Security | 1 day | 0 days | 4/19/2010 11:00 | 4/20/2010 10:30 |
Certification Plan | 1 day | 0 days | 4/19/2010 11:00 | 4/20/2010 10:30 |
Statement of Sensitivity | 1 day | 0 days | 4/19/2010 11:00 | 4/20/2010 10:30 |
Threat Risk Assessment | 1 day | 0 days | 4/19/2010 11:00 | 4/20/2010 10:30 |
Technical Solution | 1 day | 0 days | 4/19/2010 11:00 | 4/20/2010 10:30 |
Migration Strategy | 1 day | 0 days | 4/19/2010 11:00 | 4/20/2010 10:30 |
Testing Strategy | 1 day | 0 days | 4/19/2010 11:00 | 4/20/2010 10:30 |
Operational Readiness | 1 day | 0 days | 4/19/2010 11:00 | 4/20/2010 10:30 |
Enterprise change advisory board (ECAB) Request for Change Gate 1 | 1 day | 0 days | 4/19/2010 11:00 | 4/20/2010 10:30 |
Business Case Independent Review | 1 day | 0 days | 4/20/2010 10:30 | 4/21/2010 10:00 |
Enterprise change advisory board (ECAB1) | 1 day | 0 days | 4/21/2010 10:00 | 4/22/2010 9:30 |
Preliminary project approval (PPA) | 1 day | 0 days | 4/22/2010 9:30 | 4/23/2010 9:00 |
Identification close out | 1 day | 0 days | 4/23/2010 9:00 | 4/26/2010 8:30 |
Identification Stage close out document (F) | 1 day | 0 days | 4/23/2010 9:00 | 4/26/2010 8:30 |
Delivery Stage | 14 days | 0 days | 4/26/2010 8:30 | 5/13/2010 9:30 |
Planning | 3 days | 0 days | 4/26/2010 8:30 | 4/28/2010 16:00 |
Project management plan (F) | 1 day | 0 days | 4/26/2010 8:30 | 4/26/2010 17:00 |
Business Deliverables | 1 day | 0 days | 4/26/2010 8:30 | 4/26/2010 17:00 |
Business Change | 1 day | 0 days | 4/26/2010 8:30 | 4/26/2010 17:00 |
Benefits Realization Report | 1 day | 0 days | 4/26/2010 8:30 | 4/26/2010 17:00 |
Communications Plan | 1 day | 0 days | 4/26/2010 8:30 | 4/26/2010 17:00 |
Policy Change Requirement | 1 day | 0 days | 4/26/2010 8:30 | 4/26/2010 17:00 |
Release Plan | 1 day | 0 days | 4/26/2010 8:30 | 4/26/2010 17:00 |
Requirements Traceability Matrix Update | 1 day | 0 days | 4/26/2010 8:30 | 4/26/2010 17:00 |
Training Plan | 1 day | 0 days | 4/26/2010 8:30 | 4/26/2010 17:00 |
Procurement | 1 day | 0 days | 4/26/2010 8:30 | 4/26/2010 17:00 |
Detailes Scoring Grid | 1 day | 0 days | 4/26/2010 8:30 | 4/26/2010 17:00 |
Evaluation Criteria | 1 day | 0 days | 4/26/2010 8:30 | 4/26/2010 17:00 |
Request for Acquisitions Services | 1 day | 0 days | 4/26/2010 8:30 | 4/26/2010 17:00 |
Request for proposal | 1 day | 0 days | 4/26/2010 8:30 | 4/26/2010 17:00 |
Security Requirements Checklist | 1 day | 0 days | 4/26/2010 8:30 | 4/26/2010 17:00 |
Statement of Work | 1 day | 0 days | 4/26/2010 8:30 | 4/26/2010 17:00 |
Contract Review Board (CRB) Presentations | 1 day | 0 days | 4/26/2010 8:30 | 4/26/2010 17:00 |
Architecture | 1 day | 0 days | 4/26/2010 8:30 | 4/26/2010 17:00 |
Architecture Solution (Logical Version) | 1 day | 0 days | 4/26/2010 8:30 | 4/26/2010 17:00 |
Privacy | 1 day | 0 days | 4/26/2010 8:30 | 4/26/2010 17:00 |
Privacy Impact Assessment Update | 1 day | 0 days | 4/26/2010 8:30 | 4/26/2010 17:00 |
Security | 1 day | 0 days | 4/26/2010 8:30 | 4/26/2010 17:00 |
Certification Plan Update | 1 day | 0 days | 4/26/2010 8:30 | 4/26/2010 17:00 |
Conceptual Security Architecture | 1 day | 0 days | 4/26/2010 8:30 | 4/26/2010 17:00 |
Safeguard Plan | 1 day | 0 days | 4/26/2010 8:30 | 4/26/2010 17:00 |
Technical Solution | 1 day | 0 days | 4/26/2010 8:30 | 4/26/2010 17:00 |
Concept of Operations Update | 1 day | 0 days | 4/26/2010 8:30 | 4/26/2010 17:00 |
Functional Requirements | 1 day | 0 days | 4/26/2010 8:30 | 4/26/2010 17:00 |
Infrastructure Requirements | 1 day | 0 days | 4/26/2010 8:30 | 4/26/2010 17:00 |
Migration Plan | 1 day | 0 days | 4/26/2010 8:30 | 4/26/2010 17:00 |
Non-functional Requirements | 1 day | 0 days | 4/26/2010 8:30 | 4/26/2010 17:00 |
Operational Readiness | 1 day | 0 days | 4/26/2010 8:30 | 4/26/2010 17:00 |
Transition Plan | 1 day | 0 days | 4/26/2010 8:30 | 4/26/2010 17:00 |
Project charter Independent Review | 1 day | 0 days | 4/27/2010 8:00 | 4/27/2010 16:30 |
Project management plan approval (PMPA) | 1 day | 0 days | 4/27/2010 16:30 | 4/28/2010 16:00 |
Design | 4 days | 0 days | 4/28/2010 16:00 | 5/4/2010 14:00 |
Business Case Update (F) | 1 day | 0 days | 4/28/2010 16:00 | 4/29/2010 15:30 |
Project charter Update | 1 day | 0 days | 4/28/2010 16:00 | 4/29/2010 15:30 |
PCRA Update (F) | 1 day | 0 days | 4/28/2010 16:00 | 4/29/2010 15:30 |
Business Deliverables | 1 day | 0 days | 4/28/2010 16:00 | 4/29/2010 15:30 |
Architecture | 1 day | 0 days | 4/28/2010 16:00 | 4/29/2010 15:30 |
Architecture Solution (Detailed Version) | 1 day | 0 days | 4/28/2010 16:00 | 4/29/2010 15:30 |
Security | 1 day | 0 days | 4/28/2010 16:00 | 4/29/2010 15:30 |
Safeguard Plan Update | 1 day | 0 days | 4/28/2010 16:00 | 4/29/2010 15:30 |
Logical Security Architecture | 1 day | 0 days | 4/28/2010 16:00 | 4/29/2010 15:30 |
Threat Risk Assessment Update | 1 day | 0 days | 4/28/2010 16:00 | 4/29/2010 15:30 |
Technical Solution | 1 day | 0 days | 4/28/2010 16:00 | 4/29/2010 15:30 |
Data Conversion Plan | 1 day | 0 days | 4/28/2010 16:00 | 4/29/2010 15:30 |
Hardware Configuration | 1 day | 0 days | 4/28/2010 16:00 | 4/29/2010 15:30 |
Physical Data Model | 1 day | 0 days | 4/28/2010 16:00 | 4/29/2010 15:30 |
Migration Plan Update | 1 day | 0 days | 4/28/2010 16:00 | 4/29/2010 15:30 |
System Requirement Specification | 1 day | 0 days | 4/28/2010 16:00 | 4/29/2010 15:30 |
System Testing Plan | 1 day | 0 days | 4/28/2010 16:00 | 4/29/2010 15:30 |
User Acceptance Testing Plan | 1 day | 0 days | 4/28/2010 16:00 | 4/29/2010 15:30 |
Detailed Plan Independent Review | 1 day | 0 days | 4/29/2010 15:30 | 4/30/2010 15:00 |
Enterprise change advisory board (ECAB2) | 1 day | 0 days | 4/30/2010 15:00 | 5/3/2010 14:30 |
Effective project approval | 1 day | 0 days | 5/3/2010 14:30 | 5/4/2010 14:00 |
Implementation | 7 days | 0 days | 5/4/2010 14:00 | 5/13/2010 9:30 |
Product turn-over (F) | 1 day | 0 days | 5/4/2010 14:00 | 5/5/2010 13:30 |
Business Deliverables | 1 day | 0 days | 5/4/2010 14:00 | 5/5/2010 13:30 |
Business Change | 1 day | 0 days | 5/4/2010 14:00 | 5/5/2010 13:30 |
Communications Material | 1 day | 0 days | 5/4/2010 14:00 | 5/5/2010 13:30 |
Release Plan Update | 1 day | 0 days | 5/4/2010 14:00 | 5/5/2010 13:30 |
Requirements Traceability Matrix Update | 1 day | 0 days | 5/4/2010 14:00 | 5/5/2010 13:30 |
Security | 1 day | 0 days | 5/4/2010 14:00 | 5/5/2010 13:30 |
Physical Security Architecture | 1 day | 0 days | 5/4/2010 14:00 | 5/5/2010 13:30 |
Statement of Sensitivity Update | 1 day | 0 days | 5/4/2010 14:00 | 5/5/2010 13:30 |
Threat Risk Assessment Update | 1 day | 0 days | 5/4/2010 14:00 | 5/5/2010 13:30 |
Certification Evidence Report | 1 day | 0 days | 5/4/2010 14:00 | 5/5/2010 13:30 |
Certification Report | 1 day | 0 days | 5/4/2010 14:00 | 5/5/2010 13:30 |
Letter of Accreditation | 1 day | 0 days | 5/4/2010 14:00 | 5/5/2010 13:30 |
Recommendation for Accreditation | 1 day | 0 days | 5/4/2010 14:00 | 5/5/2010 13:30 |
Technical Solution | 1 day | 0 days | 5/4/2010 14:00 | 5/5/2010 13:30 |
System Testing Procedures | 1 day | 0 days | 5/4/2010 14:00 | 5/5/2010 13:30 |
User Acceptance Testing Procedures | 1 day | 0 days | 5/4/2010 14:00 | 5/5/2010 13:30 |
Data Migration Evaluation Summary | 1 day | 0 days | 5/4/2010 14:00 | 5/5/2010 13:30 |
Operations & Maintenance Plan | 1 day | 0 days | 5/4/2010 14:00 | 5/5/2010 13:30 |
Operations & Maintenance Processes | 1 day | 0 days | 5/4/2010 14:00 | 5/5/2010 13:30 |
System Testing Summary Results | 1 day | 0 days | 5/4/2010 14:00 | 5/5/2010 13:30 |
Technical Overview Document | 1 day | 0 days | 5/4/2010 14:00 | 5/5/2010 13:30 |
Operational Readiness | 1 day | 0 days | 5/4/2010 14:00 | 5/5/2010 13:30 |
Acceptance Criteria | 1 day | 0 days | 5/4/2010 14:00 | 5/5/2010 13:30 |
Platform Readiness Guide | 1 day | 0 days | 5/4/2010 14:00 | 5/5/2010 13:30 |
Release Notes | 1 day | 0 days | 5/4/2010 14:00 | 5/5/2010 13:30 |
Transition Plan Update | 1 day | 0 days | 5/4/2010 14:00 | 5/5/2010 13:30 |
Training Guides and Other Material | 1 day | 0 days | 5/4/2010 14:00 | 5/5/2010 13:30 |
User Acceptance Summary Results | 1 day | 0 days | 5/4/2010 14:00 | 5/5/2010 13:30 |
User Guide | 1 day | 0 days | 5/4/2010 14:00 | 5/5/2010 13:30 |
Construction Deployment Independent Review | 1 day | 0 days | 5/5/2010 13:30 | 5/6/2010 12:00 |
Enterprise change advisory board (ECAB3) | 1 day | 0 days | 5/6/2010 13:00 | 5/7/2010 11:30 |
Turn-over approval | 1 day | 0 days | 5/7/2010 11:30 | 5/10/2010 11:00 |
Delivery Close Out | 3 days | 0 days | 5/10/2010 11:00 | 5/13/2010 9:30 |
Close out document | 1 day | 0 days | 5/10/2010 11:00 | 5/11/2010 10:30 |
Business Deliverables | 1 day | 0 days | 5/10/2010 11:00 | 5/11/2010 10:30 |
Operational Readiness | 1 day | 0 days | 5/10/2010 11:00 | 5/11/2010 10:30 |
Service Level Agreements | 1 day | 0 days | 5/10/2010 11:00 | 5/11/2010 10:30 |
Post Implementation Review | 1 day | 0 days | 5/11/2010 10:30 | 5/12/2010 10:00 |
Close out document approval (CODA) | 1 day | 0 days | 5/12/2010 10:00 | 5/13/2010 9:30 |