Financial reporting—The Long Term Vision and Plan Annual Report 2017 to 2018
Summary of expenditures and delivery timeline
Budget | Expenditures | Forecast | ||||||
---|---|---|---|---|---|---|---|---|
Project
approval |
Expenditure
authority |
2017 to 2018
budget |
Previous years
expenditures |
2017 to 2018
expenditures |
Cumulative expenditures up to 2017 to 2018 | Planned
expenditures 2018 to 2019 table 1 note 2 |
Planned
expenditures 2019 to 2020 and future years table 1 note 2 |
|
Total Major Capital Program table 1 note 1 | 3,317.4 | 3,292.1 | 342.8 | 2,090.2 | 329.9 | 2,420.1 | 354.9 | 948.7 |
Total Recapitalization Program | 377.3 | 360.1 | 24.7 | 206.7 | 23.4 | 230.1 | 15.5 | 181.7 |
Total Building Components and Connectivity Program | 208.1 | 181.4 | 17.6 | 139.7 | 14.7 | 154.4 | 29.3 | 31.4 |
Total Security Infrastructure Program | 126.4 | 113.6 | 91.4 | 12.6 | 91.4 | 103.9 | 30.6 | 56.7 |
Total Planning Program | 228.8 | 163.1 | 9.8 | 82 | 9.8 | 91.8 | 10.7 | 43.0 |
Grand total Long Term Vision and Plan (LTVP) | 4,258.0 | 4,110.20 | 486.2 | 2,531.20 | 469.2 | 3,000.40 | 441.0 | 1,261.50 |
Table 1 Notes
|
Remarks
- Numbers may not add up due to rounding. Planned forecasts may require project approval and/or expenditure authority amendment
- New project approval process implemented in fiscal year FY 2016 to 17 which now excludes pre-planning costs from project approval
Major Capital Program
Budget | Expenditures | Forecast | |||||||
---|---|---|---|---|---|---|---|---|---|
Projects | Project approval | Expenditure authority | 2017 to 2018 budget | Previous years expenditures | 2017 to 2018 expenditures | Cumulative expenditures up to 2017 to 2018 | Planned expenditures 2018 to 2019table 2 note 2 | Planned expenditures 2019 to 2020 and future yearstable 2 note 2 | Substantial completion datestable 2 note 3 |
West Block rehabilitation (and projects related to West Block) | 862.9 | 862.9 | 111 | 631.4 | 111 | 742.4 | 117.4 | 3 | 2018 |
Wellington building renovation | 425.2 | 425.2 | 4.3 | 415.9 | 4.3 | 420.2 | 1 | 4.1 | 2016 |
Visitor welcome centre—phase 1 (and projects related) | 129.9 | 129.9 | 46.7 | 56 | 46.7 | 102.6 | 25.9 | 1.3 | 2018 |
Senate interim accommodations (Government conference centre) | 219.8 | 219.8 | 63 | 99.4 | 63 | 162.3 | 49 | 8.4 | 2018 |
Senate interim accommodations (40 Elgin) | 49.7 | 26.5 | 5 | 0.7 | 5 | 5.8 | 8 | 12.8 | 2018 |
Sir John A. Macdonald building | 99.5 | 99.5 | 0.4 | 99.1 | 0.4 | 99.5 | 0 | 0 | 2015 |
Library of Parliament | 134.1 | 134.1 | 0 | 134.1 | 0 | 134.1 | 0 | 0 | 2006 |
Centre Block major rehabilitation | 655 | 655 | 47.8 | 1.4 | 47.8 | 49.3 | 68.9 | 536.9 | TBD |
Visitor welcome centre complex | 106.5 | 106.5 | 0 | 0 | 0 | 0 | 17 | 89.6 | TBD |
Parliament Hill emergency power | 9.7 | 9.7 | 0.6 | 8.2 | 0.6 | 8.8 | 0.9 | 0 | 2017 |
Senate interim accommodation—Government Conference Centre (GCC) chamber broadcasting | 6 | 6 | 2 | 2 | 2 | 4 | 2 | 0 | 2018 |
Storm water management | 5.9 | 5.9 | 5.9 | 0 | 5.9 | 5.9 | 0 | 0 | 2018 |
Material management handling equipment | 7.4 | 7.4 | 6.9 | 0 | 6.9 | 6.9 | 0.5 | 0 | 2018 |
West Parliament Hill landscape enhancement project | 14 | 14 | 3 | 0 | 3 | 3 | 11 | 0 | 2018 |
Leases, fit-ups and othertable 2 note 1 | 591.7 | 589.6 | 46.1 | 642 | 33.2 | 675.3 | 53.3 | 292.6 | n/a |
Total Major Capital Program | 3,317.40 | 3,292.10 | 342.8 | 2,090.20 | 329.9 | 2,420.10 | 354.9 | 948.7 | |
Table 1 Notes
|
Remarks
- Numbers may not add due to rounding. Planned forecast may require project approval and/or expenditure authority amendments
- New project approval process implemented in FY 2016 to 2017 which now excludes pre-planning costs from Project Approval
Recapitalization Program
Budget | Expenditures | Forecast | |||||||
---|---|---|---|---|---|---|---|---|---|
Projects | Project approval | Expenditure authority | 2017 to 2018 budget | Previous years expenditures | 2017 to 2018 expenditures | Cumulative expenditures up to 2017 to 2018 | Planned expenditure 2017 to 2018table 3 note 1 | Planned expenditures 2019 to 2020 and future yearstable 3 note 1 | Substantial completion dates |
East Block 1867 Wing exterior rehabilitation | 80.6 | 64.4 | 6.1 | 14.2 | 6.1 | 20.3 | 8 | 36 | TBD |
Confederation Building window frame stabilization and sash rehabilitation phase 2 | 12.8 | 12.8 | 1.4 | 0.6 | 1.4 | 2 | 2 | 9.7 | 2019 |
Confederation Building mechanical and electrical upgrades | 3.9 | 3.9 | 1.4 | 0.1 | 1.4 | 1.5 | 0.9 | 1.6 | 2018 |
Escarpment drive stabilization project | 5 | 5 | 5 | 0 | 5 | 5 | 0 | 0 | 2017 |
Lighting implementation - 180 Wellington | 2.6 | 2.6 | 0.8 | 1.5 | 0.8 | 2.3 | 0.3 | 0 | 2017 |
Lighting implementation - Visitor Welcome Centre Phase 1 | 2 | 2 | 0 | 0 | 0 | 0 | 0 | 2 | TBD |
Other recapitalization | 270.6 | 269.6 | 10.1 | 190.2 | 8.9 | 199.1 | 4.4 | 132.4 | |
Total Recapitalization Program | 377.3 | 360.1 | 24.7 | 206.7 | 23.4 | 230.1 | 15.5 | 181.7 | |
Table 3 Notes
|
Remarks
- Numbers may not add due to rounding. Planned forecast may require project approval and/or expenditure authority amendments
- New project approval process implemented in FY 2016 to 2017 which now excludes pre-planning costs from Project Approval
Building Components and Connectivity Program
Budget | Expenditures | Forecast | |||||||
---|---|---|---|---|---|---|---|---|---|
Projects | Project approval | Expenditure authority | 2017 to 2018 budget | Previous years expenditures | 2017 to 2018 expenditures | Cumulative expenditures up to 2017 to 2018 | Planned expenditure 2018 to 2019table 4 note 1 | Planned expenditure 2019 to 2020 and future yearstable 4 note 1 | Substantial completion datestable 4 note 2 |
Parliament Hill pathway connectivity | 15.5 | 15.5 | 2.4 | 13.1 | 2.4 | 15.5 | 0 | 0 | 2018 |
Next generation network infrastructure—telephony | 11.9 | 11.9 | 3.9 | 6.8 | 3.9 | 10.7 | 1.2 | 0 | 2020 |
Modernization of the Parliament cable access television (CATV) | 14.0 | 4.7 | 1.8 | 1.5 | 1.8 | 3.3 | 3.4 | 7.2 | 2021 |
South of Wellington connectivity | 4.5 | 3.5 | 0.7 | 1.3 | 0.7 | 2 | 0.3 | 2.2 | 2018 |
IT Infrastructure base building upgrades | 15.2 | 6.3 | 0.9 | 0 | 0.9 | 0.9 | 3 | 11.4 | 2020 |
Datacentre disaster recovery projects | 17.6 | 17.6 | 2.1 | 0 | 2.1 | 2.1 | 4.9 | 10.6 | 2020 |
Other building components and connectivity | 129.4 | 121.9 | 5.9 | 116.9 | 3 | 120 | 16.5 | 0 | |
Total Building Components and Connectivity Program | 208.1 | 181.4 | 17.6 | 139.7 | 14.7 | 154.4 | 29.3 | 31.4 | |
Table 4 Notes
|
Remarks
- Numbers may not add due to rounding. Planned forecast may require project approval and/or expenditure authority amendments
- New project approval process implemented in FY 2016 to 2017 which now excludes pre-planning costs from Project Approval
- CATV and South of Wellington include pre-planning costs as both projects were approved before this change
Planning Program
Budget | Expenditures | Forecast | |||||||
---|---|---|---|---|---|---|---|---|---|
Projects | Project approval | Expenditure authority | 2016 to 20717 budget | Previous years expenditures | 2017 to 2018 expenditures | Cumulative expenditures up to 2017 to 2018 | Planned expenditures 2018 to 2019table 5 note 1 | Planned expenditures 2019 to 2020 and future yearstable 5 note 1 | Substantial completion dates |
Long Term Vision and Plan underground infrastructure master plan | 2.2 | 2.2 | 0.1 | 1.8 | 0.1 | 1.9 | 0.1 | 0.2 | 2017 |
Material management master plan | 1.7 | 1.7 | 0 | 1.2 | 0 | 1.3 | 0.3 | 0.1 | 2016 |
Confederation building major rehabilitation | 1.9 | 1.9 | 0.2 | 1.6 | 0.2 | 1.8 | 0 | 0 | TBD |
Block 2 redevelopment, including public use for 100 Wellington | 20 | 20 | 2.7 | 0.5 | 2.7 | 3.2 | 7.3 | 9.5 | TBD |
Long Term Vision and Plan update phases 1 and 2 | 4.1 | 4.1 | 0.1 | 0 | 0.1 | 0.1 | 1.8 | 2.2 | TBD |
Other planning | 198.9 | 133.2 | 6.6 | 76.9 | 6.6 | 83.5 | 1.2 | 31 | |
Total Planning Program | 228.8 | 163.1 | 9.8 | 82 | 9.8 | 91.8 | 10.7 | 43 | |
Table 5 Notes
|
Remarks
- Numbers may not add due to rounding. Planned forecast may require project approval and/or expenditure authority amendments
- New project approval process implemented in FY 2016 to 2017 which now excludes pre-planning costs from Project Approval
Security Infrastructure Program
Budget | Expenditures | Forecast | |||||||
---|---|---|---|---|---|---|---|---|---|
Projects | Project approval | Expenditure authority | 2017 to 2018 budget | Previous years expenditures | 2017 to 2018 expenditures | Cumulative expenditures up to 2017 to 2018 | Planned expenditures 2018 to 2019table 6 note 1 | Planned expenditures 2019 to 2020 and future yearstable 6 note 1 | Substantial completion dates |
Visitor welcome centre phase 1—Security enhancement | 17.3 | 17.3 | 15.3 | 2 | 15.3 | 17.3 | 0 | 0 | 2017 |
West Block—Security enhancement | 15.1 | 15.1 | 10.1 | 5 | 10.1 | 15.1 | 0 | 0 | 2017 |
Wellington—Security enhancement | 21.9 | 9.1 | 2.4 | 4.2 | 2.4 | 6.6 | 0.2 | 0 | 2018 |
Government Conference Centre—Security enhancement | 18 | 18 | 10 | 0.7 | 10 | 10.7 | 7.2 | 0 | 2018 |
Preparation for Secure Tunnels | 46.1 | 46.1 | 46.1 | 0 | 46.1 | 46.1 | 0 | 0 | 2018 |
Other security | 8 | 8 | 7.4 | 0.6 | 7.4 | 8.1 | 23.1 | 56.7 | |
Total Planning Program | 126.4 | 113.6 | 91.4 | 12.6 | 91.4 | 103.9 | 30.6 | 56.7 | |
Table 6 Notes
|
Remarks
- Numbers may not add due to rounding. Planned forecast may require project approval and/or expenditure authority amendments
- New project approval process implemented in FY 2016 to 2017 which now excludes pre-planning costs from Project Approval
Leased
LTVP leases | Lease project approval (LPA)table 7 note 1 | Previous years expenditures | Forecasted expenditures in 2017 to 2018 | Actual expenditures in FY 2017 to 2018 | Total expenditures to end of FY 2017 to 2018 |
---|---|---|---|---|---|
119 Queen Street | $1.2 | $3.0 | $0.5 | $0.5 | $3.5 |
131 Queen Street | $166.3 | $140.7 | $14.6 | $13.7 | $154.4 |
181 Queen Street | $59.9 | $83.4 | $7.2 | $7.0 | $90.4 |
155 Queen Street (10th Floor) | $13.6 | $4.1 | $0.5 | $0.5 | $4.6 |
155 Queen Street (6th Floor) | $0.3 | $0.2 | $0.0 | $0.0 | $0.2 |
2074-2086 Walkley Road, Trade Shops | $11.2 | $4.0 | $0.9 | $0.6 | $4.6 |
768 Belfast Road, House of Commons | $2.0 | $1.4 | $0.0 | $0.0 | $1.4 |
2455 Don Reid Drive, E-Printing | $11.1 | $6.4 | $1.3 | $0.7 | $7.1 |
1 Wellington Street—Rideau Committee Rooms | $23.6 | $7.2 | $0.5 | $0.4 | $7.6 |
C.D. Howe Building | $18.4 | $17.8 | $1.7 | $1.6 | $19.4 |
Clarica/Sun Life Building | $46.9 | $37.6 | $3.2 | $3.1 | $40.7 |
Interim Room 200—Government of Canada Conference Centre | $9.1 | $8.5 | $0.0 | $0.0 | $8.5 |
Parks Canada | $1.0 | $0.1 | $0.1 | $0.1 | $0.2 |
40 Elgin Street Chambers building | $12.1 | $0.0 | $0.5 | $0.5 | $0.5 |
Grand Total LTVP | $376.6 | $314.5 | $31.0 | $28.8 | $343.2 |
Table 7 Notes
|
Remark
Numbers may not add up due to rounding.
Figure 23: Long Term Vision and Plan annual lease costs (in millions of dollars)

Table equivalent of figure 23: Long Term Vision and Plan annual lease costs (in millions of dollars)
Fiscal year | Expenditures | Future year projections |
---|---|---|
2002 to 2003 | $0.0 | n/a |
2003 to 2004 | $0.5 | n/a |
2004 to 2005 | $5.5 | n/a |
2005 to 2006 | $6.8 | n/a |
2006 to 2007 | $17.5 | n/a |
2007 to 2008 | $24.0 | n/a |
2008 to 2009 | $24.0 | n/a |
2009 to 2010 | $26.0 | n/a |
2010 to 2011 | $28.1 | n/a |
2011 to 2012 | $29.3 | n/a |
2012 to 2013 | $30.7 | n/a |
2013 to 2014 | $30.5 | n/a |
2014 to 2015 | $30.7 | n/a |
2015 to 2016 | $31.3 | n/a |
2016 to 2017 | $29.8 | n/a |
2017 to 2018 | $28.8 | n/a |
2018 to 2019 | n/a | $29.5 |