Public Services and Procurement Canada
Quarterly Financial Report for the quarter ended June 30, 2021

On this page

1. Introduction

This Quarterly Financial Report (QFR) should be read in conjunction with the Main Estimates. It has been prepared by management as required under section 65.1 of the Financial Administration Act and in the form and manner prescribed by the Directive on Accounting Standards, GC 4400 Departmental Quarterly Financial Report. It has not been subject to an external audit or review.

1.1 Raison d'être

Public Works and Government Services Canada (PWGSC) was established effective June 20, 1996, under the department of Public Works and Government Services Act. As of November 4, 2015, PWGSC started operating as Public Services and Procurement Canada (PSPC). PSPC plays an important role in the daily operations of the Government of Canada. It supports federal departments and agencies in the achievement of their mandated objectives as their central purchasing agent, real property manager, linguistic authority, treasurer, accountant, pay and pension administrator, and common service provider. The department's vision is to excel in government operations, and its strategic outcome and mission are to deliver high-quality, central programs and services that ensure sound stewardship on behalf of Canadians and meet the program needs of federal institutions.

A summary description of the department's core responsibilities can be found in Part II of the Main Estimates.

1.2 Basis of presentation

This quarterly report has been prepared by management using an expenditure basis of accounting and a special-purpose financial reporting framework designed to meet financial information needs with respect to the use of spending authorities. The accompanying Table 3: Statement of authorities (unaudited)—For the quarter ended June 30, 2021 (in thousands of dollars) includes the department's spending authorities granted by Parliament, and those used by the department are consistent with the Main Estimates for the current fiscal year.

The authority of Parliament is required before money can be spent by the government. Approvals are given in the form of annually approved limits through appropriation acts, or through legislation in the form of statutory spending authority for specific purposes.

When Parliament is dissolved for the purposes of a general election, section 30 of the Financial Administration Act authorizes the Governor General, under certain conditions, to issue a special warrant authorizing the government to withdraw funds from the Consolidated Revenue Fund. A special warrant is deemed to be an appropriation for the fiscal year in which it is issued.

The department uses the full accrual method of accounting to prepare and present its annual departmental financial statements that are part of the departmental results reporting process. However, the spending authorities voted by Parliament remain on an expenditure basis.

1.3 Public Services and Procurement Canada's financial structure

PSPC provides services to many government departments, agencies and Crown corporations through a variety of funding mechanisms. This includes budgetary authorities that are comprised of voted and statutory authorities, as well as non-budgetary authorities. The voted budgetary authorities include operating expenditures, vote-netted revenues and capital expenditures, while the statutory authorities are mainly composed of revolving funds, employee benefit plans and payments in lieu of taxes (PILT). The non-budgetary authorities consist primarily of the Seized Property Working Capital Account (see description below).

PSPC's complex financial structure may result in significant fluctuations in authorities on a quarterly basis, which are due to timing differences that are resolved by year-end. These are summarized as follows:

For the most part, PSPC delivers its services on a cost-recovery basis, generating revenues via revolving fund ("the Funds") organizations and programs within the operating vote. These organizations and programs are mainly designed to provide services to other government organizations, and are expected to recover the cost of their operations through revenues. However, the costs incurred by the Funds are usually disbursed prior to invoicing the client, which generally occurs upon completion of a project or after services are rendered, and thus revenues maybe collected in a subsequent quarter.

PSPC manages a variety of real property projects that progress through phases from planning to funding and from procurement to construction. Historical trends have shown that expenditures against these projects are not incurred evenly throughout the year; thus, quarter-to-quarter fluctuations are normal. Such projects include the Alaska Highway in British Columbia and Yukon, and the rehabilitation of the Parliamentary Precinct in Ottawa.

PILT issued by PSPC are funded through a statutory vote and paid on behalf of other participating federal departments. Payments are subsequently recovered from the participating departments and are recorded as statutory grants in the Public Accounts of Canada. Timing fluctuations can occur between the payments and the recoveries from the other departments.

PSPC also manages seized property for the Government of Canada pursuant to the Seized Property Management Act. The financial management of this activity is undertaken through the non-budgetary Seized Property Working Capital Account. Charged to this account are expenditures and advances made to maintain and manage any seized or restrained property. PSPC recovers its costs from this account once the property owner loses the right to the property and it is disposed of.

1.4 COVID-19 pandemic

The COVID-19 pandemic represents a serious global health threat that has resulted in governments worldwide enacting emergency measures to combat the spread of the virus. PSPC has been actively engaged in supporting the Government of Canada's pandemic response, through procurements in response to an unprecedented and urgent demand for personal protective equipment (PPE), COVID-19 testing kits and supplies, vaccines and vaccination supplies and other medical equipment such as ventilators and emergency mobile medical units and beds. PSPC also received funding to operationalize the Essential Services Contingency Reserve to support the provision of PPE for essential services in Canada. COVID-19 will continue to have an impact on PSPC's financial situation for the foreseeable future as the department continues to play a central role in response and recovery efforts. PSPC secured additional funding and the required authorities to support its increased activities and ensure financial sustainability for the Government of Canada’s pandemic response.

2. Highlights of fiscal quarter and fiscal year-to-date results

2.1 Significant changes to authorities

When compared to the same quarter of the previous year, year-to-date PSPC authorities available for use increased by $957.6 million ($4,203.9 million in the first quarter of the fiscal year ending March 31, 2021 compared to $5,161.5 million in the first quarter of the fiscal year ending March 31, 2022) as reflected in Table 3: Statement of authorities (unaudited)—For the quarter ended June 30, 2021 (in thousands of dollars). Major reasons for the increase are outlined below:

Table 1: Year-over-year variances in authorities available for use (in millions of dollars)
Initiatives Operating Capital Budgetary
statutory
authorities
Total variances
Interim supply 193.0 396.8 0 589.8
Real Property Program Integrity 285.0 0 0 285.0
Supplies for the Health System (COVID-19) 650.9 0 (500.0) 150.9
Planning and Investment in PSPC's Assets Portfolio (32.7) 45.8 0 13.1
Cape Breton Operations (1.7) 0 (0.2) (1.9)
Transfer (7.5) 0 (1.4) (8.9)
Revolving Funds 0 0 (22.0) (22.0)
E-Procurement Solution (45.3) 0 (0.4) (45.7)
Other 1.3 0 (4.0) (2.7)
Cumulative variance in authorities available for use 1,043.0 442.6 (528.0) 957.6

Groupings can change between quarters due to materiality of initiatives.

Amounts may not balance with other public documents due to rounding.

The cumulative increase of $957.6 million from the first quarter of the fiscal year ending March 31, 2021 can be explained by:

Interim supply—increase of $589.8 million
The increase is due to the timing of receipt of authorities in 2020 to 2021 as compared to 2021 to 2022. In the fiscal year ending March 31, 2021, Parliamentary business was impacted as a result of the COVID-19 pandemic, which resulted in the postponement of the approval of Full Supply until December 2020. In the first quarter, PSPC received a total of eleven twelfths of the Main Estimates for the fiscal year ending March 31, 2021 for Vote 1–Operating expenditures and a total of nine twelfths for Vote 5–Capital expenditures.
Real Property Program Integrity—increase of $285.0 million
The increase is due to the timing of receipt of funding to support the operations, repairs and maintenance of the real property portfolio by addressing historical program pressures and deferred maintenance in PSPC’s Crown assets, and ensuring the long term strategic management and operations of the real property portfolio.
Supplies for the Health System (COVID-19)—increase of $150.9 million
The increase is to allow PSPC to meet expected needs related to the COVID-19 pandemic by continuing to support the Government of Canada’s evolving pandemic response. The funding is sourced from unspent COVID-19 funding in Vote 1 – Operating expenditures from the fiscal year ending March 31, 2021 carried into the fiscal year ending March 31, 2022.
Planning and Investment in PSPC's Assets Portfolio—increase of $13.1 million
The increase reflects the department’s current funding approval to plan and deliver on its capital funding plan. This funding will ensure that PSPC maintains the quality of its infrastructure for the benefit of all Canadians.
Cape Breton Operations—decrease of $1.9 million
The decrease is mainly due to a reduction in Workers’ Compensation costs related to former Cape Breton Development Corporation employees.
Transfer—decrease of $8.9 million
The decrease is due to the transfer of the Minister’s Regional Office Program from PSPC to the Privy Council Office.
Revolving Funds—decrease of $22.0 million
The decrease is mainly due to a reduction in investment requirements for the Workplace Renewal Initiative (WRI) within the Real Property Services Revolving Fund as well as GClingua, which is a linguistic services request management platform within the Translation Bureau Revolving Fund.
E-Procurement Solution—decrease of $45.7 million
The decrease is mainly due to reduced funding requirements given the current stage of the project, which is a cloud-based Electronic Procurement Solution within PSPC and an initiative from Budget 2018 to make purchasing simpler and easier to access.
Other—decrease of $2.7 million
The decrease is the result of funding variances in miscellaneous projects and activities such as the Industrial Security Systems Transformation project.

2.2 Significant changes to year-to-date net expenditures

As presented in Table 4: Departmental budgetary expenditures by standard object (unaudited)—For the quarter ended June 30, 2021 (in thousands of dollars), year-to-date total net budgetary expenditures have decreased by $364.1 million as compared to the same quarter of the previous year ($1,187.7 million in the current fiscal year compared to $1,551.8 million in the previous fiscal year).

Overall, total spending at the end of the first quarter represents 23% of annual planned expenditures for the current fiscal year compared to 37% for the first quarter of the previous year.

Table 2: Year-over-year variances in net budgetary expenditures (presented by standard object) (in millions of dollars)
Standard object June 30, 2021 Year-to-date used at quarter end June 30, 2020 Year-to-date used at quarter end Year-over-year variance
Personnel 432.3 381.6 50.7
Transportation and communications 15.7 77.1 (61.4)
Information 2.1 1.7 0.4
Professional and special services 286.1 208.8 77.3
Rentals 296.2 312.9 (16.7)
Repair and maintenance 174.0 162.8 11.2
Utilities, materials and supplies 42.5 179.1 (136.6)
Acquisition of land, buildings and works 95.6 78.6 17.0
Acquisition of machinery and equipment 13.3 14.0 (0.7)
Transfer payments 274.0 331.3 (57.3)
Public debt charges 28.6 29.9 (1.3)
Other subsidies and payments 48.3 35.6 12.7
Revenues netted against expenditures (521.0) (261.6) (259.4)
Total net budgetary expenditures 1,187.7 1,551.8 (364.1)

Comparative figures have been reclassified to conform to the current year's presentation.

Amounts may not balance with other public documents due to rounding.

The year-over-year net decrease of $364.1 million is mainly attributable to:

3. Risks and uncertainties

PSPC integrates risk management principles into business planning, decision-making and organizational processes to minimize negative impacts and maximize opportunities across our diverse range of services and operations. Risk management at PSPC is carried out in accordance with the Treasury Board Secretariat's Framework for the Management of Risk, the Management Accountability Framework, and PSPC's Policy on Integrated Risk Management.

The following key risks were identified as having a potential financial impact on PSPC's operations:

PSPC's dependency on clients' expenditures: more than half of PSPC's financial and human resources are tied directly to cost-recovered services and activities. In a context of reduced expenditures on the part of client departments and agencies, there is a risk that PSPC could face unpredictable and reduced business volumes and associated reduced resources. In response to this risk, PSPC continually adjusts to fluctuations in operational demands while maintaining the quality of its services. This includes sustaining rigorous management of revenues, expenditures, forecasting and commitment monitoring, and working closely with other departments through the client service network to identify changing requirements and their impacts on the department.

PSPC's ability to undertake and deliver complex, transformational and interdepartmental major projects and procurements: there are inherent risks in PSPC undertaking and delivering complex, transformational and interdepartmental major projects and procurements on time, within the approved budget and according to scope, which could ultimately have an impact on the department's service strategy. In order to address these risks, PSPC has implemented disciplined investment and project management processes; established service agreements and service standards with clear identification of responsibilities; ensured sound contract management; engaged early with client departments and other stakeholders; and developed the departmental Investment Plan (IP).

In 2016, the department implemented a new pay system as part of the Pay Transformation Initiative. The implementation was a major undertaking that experienced challenges. In collaboration with other departments, central agencies and union partners, the department will continue to address the recommendations related to Phoenix from the 2017 Fall report and 2018 Spring report delivered by the Auditor General of Canada to Parliament. Given the complexity of existing pay rules, systems and processes, there is a risk that the ongoing stabilization of pay administration for the Government of Canada will be slowed down by internal system or human capacity issues, or by external challenges such as large-scale changes to labour management policies. This risk may impact the timeliness and accuracy of employee pay, the integrity of pension data, and the ability for the department to continue resolving existing pay errors.

The COVID-19 pandemic has resulted in governments worldwide enacting emergency measures to combat the spread of the virus. These measures, which include the implementation of travel bans, self-imposed quarantine periods and social distancing, have caused material disruption globally resulting in an economic slowdown. While the pandemic has been ongoing for some time now, the duration and impact of the COVID-19 outbreak is still unknown at this time. As a result, it is not possible to reliably estimate the length and severity of the impact on PSPC's financial results in future periods.

4. Significant changes to operations, personnel and programs

There were no significant changes to operations, personnel and programs during the first quarter ended June 30, 2021.

Original approved and signed by:

Bill Matthews

Deputy Minister

Public Services and Procurement Canada

Gatineau, Canada

August 27, 2021

Wojo Zielonka

Assistant Deputy Minister and Chief Financial Officer

Public Services and Procurement Canada

Gatineau, Canada

August 27, 2021

Table 3: Statement of authorities (unaudited)—For the quarter ended June 30, 2021 (in thousands of dollars)
Fiscal year ending March 31, 2022 Fiscal year ending March 31, 2021
Total available for use for the year ending March 31, 2022table 3 note 1, table 3 note 2 Used during the quarter ended June 30, 2021 Year-to-date used at quarter end Total available for use for the year ending March 31, 2021table 3 note 1, table 3 note 2 Used during the quarter ended June 30, 2020 Year-to-date used at quarter end
Vote 1
Gross operating expenditures 4,689,509 896,306 896,306 3,456,489 881,693 881,693
Vote-netted revenues (1,320,046) (281,396) (281,396) (1,129,959) (101,042) (101,042)
Net operating expenditures 3,369,463 614,910 614,910 2,326,530 780,651 780,651
Vote 5—Capital expenditures 1,632,969 166,909 166,909 1,190,358 146,198 146,198
Revolving fund authorities
Real Property Services Revolving Fund
Gross expenditures 2,066,333 288,977 288,977 2,174,293 225,842 225,842
Revenues (2,062,171) (178,067) (178,067) (2,155,385) (127,253) (127,253)
Net expenditures 4,162 110,910 110,910 18,908 98,589 98,589
Translation Bureau Revolving Fund
Gross expenditures 159,497 38,750 38,750 172,866 29,480 29,480
Revenues (156,129) (30,727) (30,727) (162,322) (22,597) (22,597)
Net expenditures 3,368 8,023 8,023 10,544 6,883 6,883
Optional Services Revolving Fund
Gross expenditures 178,789 7,141 7,141 173,488 7,017 7,017
Revenues (178,860) (30,811) (30,811) (173,488) (10,692) (10,692)
Net expenditures (71) (23,670) (23,670) 0 (3,675) (3,675)
Total of all revolving funds
Gross expenditures 2,404,619 334,868 334,868 2,520,647 262,339 262,339
Revenues (2,397,160) (239,605) (239,605) (2,491,195) (160,542) (160,542)
Total revolving fund net expenditures 7,459 95,263 95,263 29,452 101,797 101,797
Other budgetary statutory authorities
Contributions to employee benefit plans 151,129 36,511 36,511 157,140 28,878 28,878
Minister of Public Services and Procurement (PSP) salary and motor car allowance 91 23 23 89 22 22
Refunds of amounts credited to revenues in previous years 0 0 0 0 0 0
Spending of proceeds from the disposal of surplus Crown assets 419 0 0 402 0 0
Payments to provide supplies for the health system 0 0 0 500,000 162,878 162,878
Payment in lieu of taxes to municipalities and other taxing authoritiestable 3 note 2 0 274,036 274,036 0 331,326 331,326
Total other budgetary statutory authorities 151,639 310,570 310,570 657,631 523,104 523,104
Total budgetary authorities 5,161,530 1,187,652 1,187,652 4,203,971 1,551,750 1,551,750
Non-budgetary authority
Seized Property Working Capital Account 0 0 0 0 0 0
Total authorities 5,161,530 1,187,652 1,187,652 4,203,971 1,551,750 1,551,750

Table 3 Notes

Table 3 Note 1

Includes only authorities available for use and approved by Parliament at quarter-end. Amounts may not balance with other public documents due to rounding.

Return to table 3 note 1 referrer

Table 3 Note 2

Consistent with the presentation in the Main Estimates, "Total available for use for the year", for both fiscal years ending March 31, 2022 and March 31, 2021, under "PILT", is presented net of planned PILT made to municipalities and the equivalent planned recoveries from other government departments. A description of PILT is provided in section 1.3 Public Services and Procurement Canada's financial structure of this report.

Return to table 3 note 2 referrer

Table 4: Departmental budgetary expenditures by standard object (unaudited)—For the quarter ended June 30, 2021 (in thousands of dollars)
  Fiscal year ending March 31, 2022 Fiscal year ending March 31, 2021
Planned expenditures for the year ending March 31, 2022table 4 note 1, table 4 note 2 Expended during the quarter ended June 30, 2021 Year-to-date used at quarter end Planned expenditures for the year ending March 31, 2021table 4 note 1, table 4 note 2 Expended during the quarter ended June 30, 2020 Year-to-date used at quarter end
Expenditures
Personnel 1,627,865 432,297 432,297 1,510,066 381,606 381,606
Transportation and communications 97,843 15,700 15,700 79,010 77,138 77,138
Information 20,543 2,059 2,059 14,865 1,627 1,627
Professional and special services 2,251,036 286,060 286,060 1,874,086 208,779 208,779
Rentals 1,282,961 296,241 296,241 990,693 312,889 312,889
Repair and maintenance 1,275,967 174,019 174,019 1,288,779 162,825 162,825
Utilities, materials and supplies 911,359 42,470 42,470 742,802 179,064 179,064
Acquisition of land, buildings and works 652,672 95,596 95,596 585,242 78,593 78,593
Acquisition of machinery and equipment 199,886 13,313 13,313 167,353 14,003 14,003
Transfer paymentstable 4 note 2 0 274,037 274,037 0 331,326 331,326
Public Debt charges 92,345 28,564 28,564 110,570 29,848 29,848
Other subsidies and payments 466,259 48,297 48,297 461,659 35,636 35,636
Total gross budgetary expenditures 8,878,736 1,708,653 1,708,653 7,825,125 1,813,334 1,813,334
Less revenues netted against expenditures
Revolving funds revenues (2,397,160) (239,605) (239,605) (2,491,195) (160,542) (160,542)
Vote-netted revenues (1,320,046) (281,396) (281,396) (1,129,959) (101,042) (101,042)
Total revenues netted against expenditures (3,717,206) (521,001) (521,001) (3,621,154) (261,584) (261,584)
Total net budgetary expenditures 5,161,530 1,187,652 1,187,652 4,203,971 1,551,750 1,551,750

Table 4 Notes

Table 4 Note 1

Includes only authorities available for use and approved by Parliament at quarter-end. Amounts may not balance with other public documents due to rounding.

Return to table 4 note 1 referrer

Table 4 Note 2

Consistent with the presentation in the Main Estimates, "Planned expenditures for the year" for both fiscal year ending March 31, 2022 and year ended March 31, 2021, under "Transfer payments", are presented net of planned PILT made to municipalities and the equivalent planned recoveries from other government departments. A description of PILT is provided in section 1.3 Public Services and Procurement Canada's financial structure of this report.

Return to table 4 note 2 referrer

Date modified: