Vendor Name WEDLER ENGINEERING LLP
Reference Number 700332785
Contract Date 2015-08-17
Description of Work 420 - Engineering Services not Elsewhere Specified
Contract Period - From 2015-08-11
Contract Period - To 2016-03-31
Delivery Date
Contract Value $75,915.84
Total Amended Contract Value $310,629.96
Comments The purpose of this contract relates to the existing maintenance compound at Rogers Pass, BC, and several infrastructure upgrades that are required.There are drainage and grading issues that require resolution to ensure proper site drainage and protection of the adjacent Rogers Creek. The water supply system requires some alterations to connect to a new well source to reduce operating costs. Amendments are due to the following: 1. Resurfacing of the driving surface to promote stormwater drainage including multiple detention facilities and culverts to ensure proper site drainage and protection of the adjacent Rogers Creek. 2. Replacement of the existing fuel storage and dispensing facilities 3. Replacement of the sanitary sewer pipe network 4. Extension upgrades to the water treatment plant. This contract was competitively sourced.